Last week I talked about the value of construction supervision and resolving construction challenges while on site (and how I enjoy these opportunities). I had one of those opportunities in Harbin during a site inspection of an 800-seat concert hall for which ARD designed the acoustics. It was fantastic to see another venue under construction.

The hall still has a long way to go before opening, and the absorption coefficients of the proposed seats didn’t quite match our specification. But the seat prototypes looked good and made sense from a design point of view. So what difference would they actually make to the acoustics of the hall?
Some of the finishes had yet to be procured, so we still had room to make adjustments. We put the absorption data for the proposed seats into our ODEON model, checked the impact on the hall acoustics and adjusted the finishes where needed.
It’s something we do fairly regularly as acoustic consultants, but working through it on site with the architect goes a long way towards building trust and friendship. All you need to do is…
- Realise it’s not about you and your specifications.
- Roll up your sleeves and troubleshoot (get lunch delivered if it takes a while).
- Remember your first principles in acoustics and engineering.
- Remember there are many ways to achieve the same outcome.
I’m now looking forward to sitting in those seats with the architect and hearing the result.
PS: Massive kudos to the construction team. It was −15 °C outside and frankly I could barely hold my notebook and phone. How they managed to handle steel poles, swing hammers and lift GRG panels in that cold is beyond me.